Which statement best describes the Should-Cost and Will-Cost concepts?

Prepare for the PMT 4910 Advanced Certification. Study with multiple choice questions, each with explanations. Boost your confidence and get ready for your exam!

Multiple Choice

Which statement best describes the Should-Cost and Will-Cost concepts?

Explanation:
Should-Cost is the target cost defined from cost analysis and broken down into specific, discrete, and measurable actions or initiatives that you can implement to achieve savings. Will-Cost is the estimate of what the project will actually cost if you proceed with the current plan, supplier quotes, and market conditions. The best statement captures the idea that Should-Cost consists of concrete levers you can pull to realize savings against the Will-Cost baseline. The other descriptions either mischaracterize Should-Cost as a life-cycle cost, invert the savings relationship, or focus only on tracking Will-Cost without the actionable savings initiatives.

Should-Cost is the target cost defined from cost analysis and broken down into specific, discrete, and measurable actions or initiatives that you can implement to achieve savings. Will-Cost is the estimate of what the project will actually cost if you proceed with the current plan, supplier quotes, and market conditions. The best statement captures the idea that Should-Cost consists of concrete levers you can pull to realize savings against the Will-Cost baseline.

The other descriptions either mischaracterize Should-Cost as a life-cycle cost, invert the savings relationship, or focus only on tracking Will-Cost without the actionable savings initiatives.