Which equation represents Schedule Variance (SV) in Earned Value Management?

Prepare for the PMT 4910 Advanced Certification. Study with multiple choice questions, each with explanations. Boost your confidence and get ready for your exam!

Multiple Choice

Which equation represents Schedule Variance (SV) in Earned Value Management?

Explanation:
Schedule Variance shows how the project’s actual progress compares to what was planned, by comparing earned value to planned value. The correct equation is SV = EV − PV. If earned value (EV) is higher than planned value (PV), SV is positive, meaning you’re ahead of schedule. If EV is lower than PV, SV is negative, indicating you’re behind schedule; if they’re equal, SV is zero and you’re on schedule. For example, with PV of 100 and EV of 120, SV is 20 (ahead by 20). With PV of 120 and EV of 100, SV is −20 (behind by 20).

Schedule Variance shows how the project’s actual progress compares to what was planned, by comparing earned value to planned value. The correct equation is SV = EV − PV. If earned value (EV) is higher than planned value (PV), SV is positive, meaning you’re ahead of schedule. If EV is lower than PV, SV is negative, indicating you’re behind schedule; if they’re equal, SV is zero and you’re on schedule. For example, with PV of 100 and EV of 120, SV is 20 (ahead by 20). With PV of 120 and EV of 100, SV is −20 (behind by 20).

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy